Note: The easiest way to accomplish step 3 is to assemble the unit on it's side. Use a helper when lifting the structure to the upright position.
Step 4: With the unit in the upright position we are ready to level and brace it. Level the first floor on the ground. Using a level, temporarily plumb and brace the vertical uprights, while 45 degree braces are installed on the first floor that are shown in the picture. Cut these 24" long with a 45 degree angle in each end. Bolt these to the bottom of the second floor joists and the 4x4 upright as shown.
Step 5: Now it's time to install the plywood floor. Add 3 1/2" long nailers to the sides of the 4x4 uprights at the spot where the plywood floor meets the upright. (the cut out is necessary to allow the upright post to pass through the plywood floor). If you do not add these nailers the floor will be springy. Measure, cut and install the plywood floor on both floors. Use pressure treated 5/8" plywood if possible. (1/2" will work if 5/8" cannot be located)
|